Overview of the project
The digester houses over 460,000 gallons (2,100 m³) of liquid waste, making this a significant undertaking from both a logistical and safety perspective.
To avoid disruption and ensure cost-effective implementation, a detailed plan was put in place to carry out the cleaning and inspection process during the annual distillery shutdown period. This included:
- Tank Emptying;
- Isolation of the AD Tank;
- Pre-inspection Tank Nitrogen Purge;
- Initial Tank Clean (Carried out from ground level);
- Scaffolding for Cleaning and Inspection;
- Tank Clean (Internal tank walls utilising the erected scaffold);
- Tank Inspection;
- Remove scaffolding;
- Post-inspection Tank Nitrogen Purge;
- Re-seeding of the AD Tank.
Special consideration and provisions have been made to ensure the highest standards of process safety, minimise waste and support the re-seeding of the plant during commissioning.